Risk Matrix Calculator

Turn likelihood and consequence ratings into a risk score, level and recommended action on a 5 x 5 matrix.

Other ToolsUpdated 2026-11-184 min read
Risk Matrix Calculator
How likely is the event to occur?
How bad would the outcome be?
Risk score
...
Risk level...
Suggested action...
Ratings used...

What it does

A risk matrix is a simple way to put different risks in order. You score how likely an event is and how serious its outcome would be, then multiply the two numbers. The product places the risk on a grid, and the grid tells you which ones need attention first. ISO 31000 defines the level of risk as the magnitude of a risk expressed as a combination of consequences and their likelihood, which is exactly what this tool puts on a number.

Both scales run from 1 to 5 here. On the likelihood axis, 1 means rare and 5 means almost certain. On the consequence axis, 1 means minor and 5 means severe. The words matter more than the numbers, because the person filling in the grid has to decide what each word means for their own setting. A minor delay on a household task is not the same as a minor delay on a hospital operating theatre.

The product runs from 1 to 25. This page splits that range into five bands: 1 to 4 Low, 5 to 9 Moderate, 10 to 14 High, 15 to 19 Very High and 20 to 25 Extreme. Each band carries an action, from monitoring a Low risk through to stopping or escalating an Extreme one. The bands are a common convention, not a rule from any standard, so an organisation can set its own cutoffs.

The matrix is deliberately coarse. Two risks with the same score may need very different responses, and a low score does not make a risk harmless. International Civil Aviation Organization guidance on applying ISO 31000 notes that organisations are expected to tailor their risk criteria to their own context. Treat the result as a starting point for a conversation, not a final verdict.

This calculator gives the score, the band and a suggested action for one risk at a time. It does not store a register, weigh risks against a budget, or track how a score changes after a control is added. Those steps belong in a fuller risk process, but the multiplication here is the same arithmetic that sits at the heart of it.

How to use

  1. Describe the risk in one sentence so that the likelihood and consequence refer to the same event.
  2. Choose a likelihood from 1, rare, through 5, almost certain, using your own records or expert judgement.
  3. Choose a consequence from 1, minor, through 5, severe, judging the outcome if the event happens.
  4. Read the risk score, which is likelihood multiplied by consequence.
  5. Check which band the score falls in and note the suggested action for that band.
  6. Repeat for the other risks on your list and sort by score, then review any ties by hand.

Formula

Risk score = Likelihood x Consequence, with each rating an integer from 1 to 5. The product, from 1 to 25, is matched to a band that carries an action.
L
Likelihood rating, an integer from 1 (rare) to 5 (almost certain).
C
Consequence rating, an integer from 1 (minor) to 5 (severe).
S
Risk score, the product L x C, an integer from 1 to 25.
B
Risk band chosen from the score: Low, Moderate, High, Very High or Extreme.
A
Suggested action attached to the band, from monitor to stop or escalate.

The scores on the two axes are ratings, not probabilities or losses, so the product is an ordinal label rather than a measured quantity. The band cutoffs used here, 4, 9, 14 and 19, are a widely used 5 x 5 convention and can be changed to suit an organisation. Because several pairs share a product, always record L and C alongside S so the reasoning stays visible.

Worked example

Example: a likely event with a serious outcome

Defaults: likelihood 4, Likely, and consequence 3, Serious. A delivery delay of a key part has happened often before and would hold up a production line for a shift.

  1. Read the likelihood rating from the first dropdown: 4, Likely.
  2. Read the consequence rating from the second dropdown: 3, Serious.
  3. Multiply the two ratings: 4 x 3 = 12.
  4. Compare 12 with the band cutoffs. It is above 9 and below 15, so it sits in the 10 to 14 High band.
  5. The High band calls for Treat soon, meaning a response should be planned and assigned.
  6. The tool shows a risk score of 12, a level of High, an action of Treat soon and the ratings Likelihood 4 of 5, Consequence 3 of 5.

Reference table

Risk score grid for all likelihood and consequence pairs on a 5 x 5 matrix
Likelihood / Consequence1 Minor2 Moderate3 Serious4 Major5 Severe
1 Rare12345
2 Unlikely246810
3 Possible3691215
4 Likely48121620
5 Almost certain510152025

Limits

  • The score is a product of two judgements, not a probability or an expected loss, so it cannot be read as a chance of harm.
  • Different pairs can produce the same score, so two risks rated 12 may need quite different controls.
  • The band cutoffs are a convention rather than a standard requirement, and other organisations may set different edges.
  • The tool looks at one risk in isolation and does not capture how several risks combine or correlate.

Common mistakes

  • Treating a score of 12 as a 12 percent chance of the event happening.
  • Swapping the two axes and assuming the answer changes, when multiplication gives the same product either way.
  • Using extreme ratings for every risk, which flattens the grid and hides the risks that really matter.
  • Forgetting to write down the likelihood and consequence beside the score, so the reason for the rating is lost.
  • Assuming a Low band means no action is needed, when it usually means the risk should be watched.

Try it yourself

Quick checks. Answers sit tucked under each question.

A risk is rated likelihood 1, consequence 5. What score and band does it get?

The score is 1 x 5 = 5, which falls in the 5 to 9 Moderate band. Suggested action: Plan a response. Note that the same score comes from 5 x 1, a very different risk.

What score does a likelihood of 5 and a consequence of 4 produce, and what should you do?

The score is 5 x 4 = 20, in the 20 to 25 Extreme band. The suggested action is Stop or escalate before work continues.

A risk scores 3 from likelihood 3 and consequence 1. Where does it sit?

The score is 3 x 1 = 3, inside the 1 to 4 Low band. The suggested action is Monitor.

Questions

What is a risk matrix?

A grid that pairs how likely an event is with how serious its outcome would be. Multiplying the two ratings gives a score used to put risks in order.

Why multiply rather than add the two ratings?

Multiplication makes a high score on both axes stand out sharply. Addition would let a severe but rare risk score the same as a mild but frequent one, which most teams want to separate.

Where do the band cutoffs come from?

They are a common 5 x 5 convention: 1 to 4 Low, 5 to 9 Moderate, 10 to 14 High, 15 to 19 Very High and 20 to 25 Extreme. Standards such as ISO 31000 ask each organisation to set its own criteria.

Is a score of 12 a probability?

No. It is a label built from two ratings on an ordered scale. It tells you where a risk sits relative to others, not how likely it is in percentage terms.

What if I disagree with the suggested action?

The action is a prompt, not a rule. It reflects the band only. Your own tolerance, legal duties and available controls should decide what you actually do.

Can I use a 4 x 4 or 7 x 7 matrix instead?

Yes, many teams do. This page fixes both axes at 1 to 5 so the scores and bands stay consistent. For a different grid you would need different cutoffs.

Sources

How this page was checked. The formula above was matched against the cited sources, and the worked example was run through the tool on this page before publishing. If you spot an error, contact us so we can fix it and note the correction.