Reorder Point Calculator
Find the inventory level at which a new order should be placed from demand, lead time and safety stock.
What it does
A reorder point is the stock level that triggers a new order. If you wait until the shelves are empty, the lead time between ordering and receiving leaves a gap with nothing to sell. The reorder point is set high enough that the remaining stock covers expected demand while the order is on its way, with a buffer for surprises.
The calculation has two parts. Expected demand during lead time is the average demand rate multiplied by the lead time. Safety stock is added on top. When on hand inventory falls to that combined level, a new order is placed so it arrives just as the buffer is being used.
The time basis has to match. If demand is measured per day, lead time must be in days. If demand is per week, convert the lead time to weeks first. Mixing the two is the most common source of a wildly wrong reorder point, and the tool cannot detect it because the arithmetic still works.
Safety stock is a separate design choice. A larger buffer reduces the chance of a stockout but ties up cash in inventory. It should reflect the variability of demand and lead time, the cost of a stockout and the service level the business wants. The tool accepts any safety stock you choose and adds it to the lead time demand.
This is the deterministic version of the idea. It treats demand and lead time as fixed averages and puts all the uncertainty into the safety stock figure. More advanced models estimate that buffer directly from demand variability and a target service probability. The reorder point is also not the order quantity, which depends on costs and order intervals and is often calculated with an economic order quantity model.
How to use
- Choose a time basis, such as a day, and use it for both demand and lead time.
- Enter the average number of units sold or used per period.
- Enter the number of periods between placing and receiving an order.
- Enter the safety stock you want to hold as a buffer.
- Read the reorder point and the demand expected during the lead time.
- Review the safety stock when demand or supplier lead times change.
Formula
- d
- Average demand per period, in units.
- L
- Lead time in the same periods as demand.
- SS
- Safety stock in units, held to cover uncertainty.
- ROP
- Reorder point in units, the stock level that triggers an order.
When demand and lead time are certain, safety stock can be zero and the reorder point is simply d times L. With variable demand or lead time, safety stock is usually estimated from a target service level, and the tool leaves that choice to you. If supply is unreliable, review the lead time input often, since a longer lead time raises the reorder point even when demand is unchanged.
Worked example
Example: 25 units per day, 6 day lead time and 40 units of safety stock
Defaults: demand 25 units per period, lead time 6 periods and safety stock 40 units.
- Multiply demand by lead time: 25 x 6 = 150 units.
- That 150 is the expected demand while the order is in transit.
- Add safety stock: 150 + 40 = 190 units.
- The tool shows reorder point 190 units, lead time demand 150.0 units and safety stock 40 units.
- When stock on hand reaches 190 units, it is time to place the next order.
Reference table
| Lead time | Lead time demand | Reorder point |
|---|---|---|
| 2 days | 50.0 units | 90 units |
| 4 days | 100.0 units | 140 units |
| 6 days | 150.0 units | 190 units |
| 8 days | 200.0 units | 240 units |
| 10 days | 250.0 units | 290 units |
Limits
- Treats demand and lead time as fixed averages and puts all uncertainty into the chosen safety stock.
- Does not calculate the order quantity or the economic order quantity.
- Ignores capacity limits, minimum order sizes and quantity discounts.
- Assumes a single stock location and one supply source.
Common mistakes
- Using daily demand with a lead time in weeks without converting one of them.
- Confusing the reorder point with the order quantity.
- Setting safety stock to zero when demand or lead time is clearly variable.
- Forgetting to raise the reorder point when a supplier becomes slower.
- Ignoring seasonal changes in the demand rate.
Try it yourself
Quick checks. Answers sit tucked under each question.
Demand 40 per day, lead time 5 days, safety stock 60. What is the reorder point?
Lead time demand is 40 x 5 = 200.0 units. Adding 60 gives a reorder point of 260 units.
Demand 12.5 per day, lead time 4 days, safety stock 25. What does the tool show?
Lead time demand is 12.5 x 4 = 50.0 units, so the reorder point is 50 + 25 = 75 units.
If there is no demand during lead time and safety stock is 40, what is the result?
Lead time demand is 0.0 units and the reorder point equals the safety stock of 40 units.
Questions
What is a reorder point?
It is the inventory level at which a new order is triggered so that stock arrives before the remaining supply runs out.
How is it different from safety stock?
Safety stock is the extra buffer held for uncertainty. The reorder point is the total level including both expected lead time demand and that buffer.
What if demand is seasonal?
Use a demand rate that reflects the coming period rather than a long term average, and review the point as the season changes.
Does the reorder point tell me how much to order?
No. That is the order quantity, usually chosen with an economic order quantity model or a target coverage period.
Why does a longer lead time raise the point?
More stock is consumed while waiting for the order, so the trigger has to happen earlier to avoid running out.
Can I use this for a service business?
Yes, whenever you replenish a stock item with a measurable demand rate and a delivery delay.