Modified Internal Rate of Return Calculator
Find MIRR from the present value of outflows, the future value of inflows and the project life.
What it does
The modified internal rate of return was developed to fix two weaknesses of the ordinary IRR. Ordinary IRR assumes that interim cash flows are reinvested at the IRR itself, which is often unrealistic, and projects with alternating signs can have several IRRs. MIRR replaces those assumptions with explicit finance and reinvestment rates.
The standard calculation discounts all negative cash flows to time zero at the finance rate and compounds all positive cash flows to the end of the project at the reinvestment rate. The modified rate is the single rate that links those two adjusted values over the project life.
This page takes the two adjusted values as inputs. If you already have the present value of outflows and the future value of inflows from a spreadsheet or a separate calculation, the tool applies the final root and expresses the answer as a percentage. It does not recompute those two values from a raw cash flow series.
In the default example, outflows have a present value of one hundred thousand and inflows grow to one hundred eighty thousand over five years. The ratio is 1.8, and its fifth root minus one is about 12.47 percent.
Finance and reinvestment rates should reflect the firm's actual borrowing cost and the return available on reinvested cash. Choosing them badly can make MIRR as misleading as the original measure, so document the assumptions behind both adjusted values.
How to use
- Discount all negative cash flows to time zero at your finance rate.
- Compound all positive cash flows to the project end at your reinvestment rate.
- Enter the resulting present value of outflows.
- Enter the resulting future value of inflows.
- Enter the number of years in the project.
- Read MIRR and the ratio of terminal to initial value.
Formula
- FV positive
- Positive cash flows compounded to the end at the reinvestment rate.
- PV negative
- Negative cash flows discounted to time zero at the finance rate.
- n
- Number of years in the project.
- MIRR
- Modified internal rate of return per year.
The tool expects the present value of outflows as a positive amount. Both adjusted values must be consistent with the same project end date. For a series with observations at times zero through n, the exponent is one over n rather than one over n plus one.
Worked example
Example: 100,000 outflows, 180,000 inflows and five years
Defaults: present value of negatives 100,000, future value of positives 180,000 and life 5 years.
- Divide terminal value by initial value: 180,000 / 100,000 = 1.8.
- Take the fifth root: 1.8^(1/5) = 1.1247.
- Subtract one: 0.1247.
- Convert to percent: 12.47 %.
- The tool shows 12.47 %, 1.800 and 5 years.
Reference table
| Future value of inflows | Ratio | MIRR |
|---|---|---|
| $120,000 | 1.2 | 3.71 % |
| $150,000 | 1.5 | 8.45 % |
| $180,000 | 1.8 | 12.47 % |
| $250,000 | 2.5 | 20.11 % |
Limits
- Takes already adjusted values rather than a raw cash flow series.
- Requires a positive present value of outflows.
- Assumes one positive terminal value and a single project life.
- Sensitive to the chosen finance and reinvestment rates.
Common mistakes
- Entering raw cash flows instead of the present and future adjusted values.
- Using ordinary IRR assumptions with MIRR inputs.
- Forgetting to compound positives to the project end.
- Using an inconsistent project end for the two values.
- Comparing MIRR values built with different reinvestment rates.
Try it yourself
Quick checks. Answers sit tucked under each question.
If terminal inflows are 150,000 with the other defaults unchanged, what is MIRR?
The ratio is 1.5 and the fifth root minus one is 8.45 percent.
Why is MIRR often preferred to IRR?
It uses explicit finance and reinvestment rates and gives a single answer even for cash flows with several sign changes.
What happens if the future value of inflows is zero?
MIRR is negative 100 percent, because the terminal ratio is zero. The tool accepts the value and reports the result.
Questions
What does MIRR stand for?
Modified internal rate of return.
How does it differ from IRR?
It uses separate finance and reinvestment rates and avoids multiple solutions for unconventional cash flows.
What is the finance rate?
The rate used to discount negative cash flows back to time zero, often the firm's borrowing cost.
What is the reinvestment rate?
The rate used to compound positive cash flows to the end of the project.
Does this tool compute those rates?
No. It expects the already adjusted present and future values as inputs.
Which MIRR should I prefer?
Higher is better for independent value creating projects, assuming the same assumptions and risk.
Sources
- Xavier University finance faculty: MIRR, The Means to an End?
- Northwestern University, MATLAB Financial Toolbox MIRR documentation
- ACCA Global: Modified internal rate of return